AASHTO LRFD Bridge Design Specifications SI units 4th Edition 2007에서
C5.9.5.3에 다음과 같은 내용이 있다.
The approximate lump sum estimates of timedependent prestress losses given in Table 1 reflect values and trends obtained from a computerized timestep analysis of a large number of bridges and building members designed for a common range of variables, namely:
Ultimate concrete creep coefficient ranging from 1.6 to 2.4,
Ultimate concrete shrinkage coefficient ranging from 0.0004 to 0.0006 (mm/mm),
Relative humidity ranging from 40 to 100 percent,
Moist-curing or steam-curing of concrete, and
A PPR ranging from 0.2 to 1.0.
아래 PCI논문을 보면 PPR에 대한 내용이 나온다.
PPR=Aps fpy / ( Aps fpy + As fy )
https://www.pci.org/PCI_Docs/Publications/PCI%20Journal/1993/May/Prestress%20Losses%20in%20Partially%20Prestressed%20High%20Strength%20Concrete%20Beams.pdf