    Formwork Removal Times


    1) The period for columns, walls, vertical
    formworks - 16-24 hrs.


    2) The period for Soffit formwork to slabs - 3
    days (props to be refixed after removal)


    3) The period for Soffit to beams props- 7 days
    (props to refixed after removal)


    4) Beams spanning up to 4.5m-7 days


    5) Beams spanning over 4.5m -14 days


    6) Arches spanning up to 6m -14 days


    7) Arches spanning over 6m - 21 days