Formwork Removal Times


1) The period for columns, walls, vertical
formworks - 16-24 hrs.


2) The period for Soffit formwork to slabs - 3
days (props to be refixed after removal)


3) The period for Soffit to beams props- 7 days
(props to refixed after removal)


4) Beams spanning up to 4.5m-7 days


5) Beams spanning over 4.5m -14 days


6) Arches spanning up to 6m -14 days


7) Arches spanning over 6m - 21 days